Repairs to Blue Mountains line opens up regional services

Work to repair the Blue Mountains line following fires and heavy rains earlier this year has taken a major step forward.

A full timetable of regional trains can now run to and from Sydney, with a temporary signalling system installed, said a Sydney Trains spokesperson.

“The temporary signalling system uses axle counters to enable diesel freight and regional trains to operate between Mount Victoria and Lithgow,” the spokesperson said.

The line is a vital link between famers in the rest of the country and resources exporters, and the Sydney basin and Port Botany. The line also provides important connectivity for inland communities.

“Freight operators can now run more trains along the vital corridor with greater track access times. NSW TrainLink is able to run a full timetable for diesel passenger trains, including the second Bathurst Bullet,” said the Sydney Trains spokesperson.

The Blue Mountains line was hit hard in the bushfires of late 2019 and early 2020 with kilometres of track knocked out of commission. Buses have been replacing trains since then, with limited freight and passenger services resuming in late January.

The Sydney Trains spokesperson said Intercity trains, which rely on overhead electrical power, will return to the line once works are complete.

“Works to repair the existing signalling system and overhead electric supply to run Intercity trains to Lithgow continue.”